General
Terms
a.
The payment of fees to the Local Authority is based on
the scale charge for the submission of a Building Notice.
Clients should confirm that the submission of a Building
Notice relating to the proposed works is acceptable to
the Local Authority Building Control. Any additional costs
relating to the provision of information requested by
the Local Authority (calculations, site investigations
etc.), or alterations to the works in order to achieve
compliance, will be charged in addition to the costs indicated
in item 6 above.
b. Unless you are a limited company and we have agreed
to provide a credit facility, we will require a payment
of 50% of the contract value prior to commencement on
site. In the case of upfront payment, we will issue you
with an invoice to cover this amount when we receive a
written confirmation order or our ‘Acceptance of
Tender’ form enclosed with the estimate.
c. No allowance has been made for the issue of, or any
costs in connection with compliance with, the requirements
of any Party Wall Notice. All costs in connection with
the appointment of Party Wall Surveyor’s shall be
met by the client.
d. All sums quoted will be subject to VAT at the rate
ruling at the time the works are carried out.
e. Unless specified in our tender, no allowance has been
made for main contractor discount. The main contractor
must ensure they allow for this item separately as an
additional cost or negotiate with Fastrack™ prior
to acceptance of our estimate. Any offer letter made to
Fastrack™ stating the deduction of this fee from
our tender without written agreement will not be accepted
irrespective if commencement on site by Fastrack™
has taken place.
f. Where applicable very effort is made to match the colour
and texture of new pointing and/or rendering with the
existing. However, shade and texture and finish variations
are inevitable due to variations in sand and gravels and
because of the effects of weathering. An absolute match
cannot, therefore, be guaranteed.
g. Where applicable, due to the nature of existing render
applications it is difficult when completing a site survey
to determine the thickness and condition of the existing
render. In view of this, all estimates will be based on
the assumption that the render finish is well bonded to
the masonry and will be a thickness of 12mm or less. Should
it become apparent when starting on site that the render
is thicker than this we will notify the client/customer/specifier
of this situation as it may be necessary to involve additional
depth, specialist cutting equipment or it may be required
for the render to be removed to the areas being repaired.
This work will involve additional costs, which will be
charged at our Daywork rate.
h. Where applicable, within our estimate for render finishes,
we have allowed for localised repairs only (only where
specified repairs are being completed by us). Where render
has de-bonded every effort will be made to minimise the
damage caused during our drilling and cutting procedures
but should additional damage take place beyond a localised
repair, we reserve the right to recover any additional
costs involved. Should we have concerns regarding the
render we will notify you at our earliest opportunity.
i. Dayworks: Plant and materials required above that allowed
in the estimate will be charged at cost plus 30%.
j. Dayworks: Additional labour required above that included
in the estimate will be charged at an all-in rate per
man/hour worked, of £40.00.
k. Attention is drawn in particular to the notes under
‘Efficacy’ attached.
l. Fixtures and Fittings – Where applicable Fastrack™
have assumed when submitting their tender unless clearly
stated by us in our estimate that the customer will take
all necessary precautions to remove all personal items
from shelves, table tops or similar, take down curtains,
pictures, electrical items, lamp bases, remove plant pots,
garden furniture etc to all rooms/areas where repairs
are being completed. Though we will endeavour to take
as necessary precautions to protect with dust sheets all
large items of furniture, we are unable to take any responsibility
for any damage that may occur to items left in the rooms
that could have been cleared by the customer prior to
works commencing.
m. Where internal work is being carried out, it is assumed
that all making good will be carried out by others, unless
specifically included in the estimate, if such works are
required then on receipt of instructions these works will
be carried out as a variation based on a further estimate
or dayworks plus materials as mentioned above.
n. The tender has been based on continuous working –
Phased or disrupted working (unless agreed to in writing
prior to commencement on site) is likely to incur additional
costs which will be charged in accordance with our terms
and conditions and may also include additional costs for
return visits.
Partial
Underpinning
a. By underpinning a wall the risk of continuing movement
of the foundation is significantly reduced. Unless the
whole of the structure is underpinned, there can be no
guarantee that further movement will not occur in parts
of the structure that have not been underpinned, or not
underpinned to the full design depth (e.g. ‘step-up’
bases).
b. Where the Company has not been provided with a specification
by or on behalf of the employer, due to the expense of
underpinning and the limitations of insurance policies
it has, in preparing its proposals, restricted the underpinning
to those parts of the structure that it considers indicate
an unacceptable degree of differential movement. Whilst
this extent of underpinning should be sufficient to restore
the stability to the structure as a whole, it is possible
that the offending ground conditions exist under other
parts of the property or adjacent structures, or may do
in the future. The Company cannot guarantee the continuing
stability of foundations, which are not supported by the
Company’s deeply founded underpinning. The Employer
may request the cost of amending the proposals as required.
c. Where the Employer wishes only partial underpinning
to be carried out, he/she should ensure before contracting
to carry out the works that he/she will be able to obtain
adequate and comprehensive Insurance cover for the whole
of the property.
Structural Repairs
a.
Underpinning involves the transfer and redistribution
of the imposed loads of the structure onto a new supporting
medium. Some relief of inherent stresses and resettlement
of the structure may occur as a result. It is generally
recommended that the schedule of superstructure repair
is not completed until after the underpinning work is
completed, and that superstructure repairs are not commenced
until 12 weeks after the underpinning has been completed.
b. In order to obtain the full benefit of the underpinning
operation, it is essential that fractures are properly
repaired in order to ensure full structural integrity
and prevent further movement across the crack in the future
as a result of local stresses. Advice on adequate repair
is available from the Company if required.
c. Where areas of plaster are removed and replaced, thorough
drying out may take many weeks. We do not recommend the
application of ‘non-breathable’ finishes (e.g.
vinyl wallpaper) for at least 8 weeks after plastering.
The application of such finishes before thorough drying
out will be at the Employer’s risk.
Internal Works
a. An inevitable degree of dust, dirt, and disturbance
is created during underpinning. Where internal works are
to be carried out, or where internal access is required,
the Employer is advised to ensure that all carpets, furnishings,
fitments and the like are removed prior to commencement
and replaced following completion. Unless specifically
included in the Estimate, these items are deemed to be
carried out by others at the Employer’s expense.
In addition, a suitable allowance should be made for the
reinstatement of internal decorations where such provisions
are not specifically included in the Estimate.
Plumbing and Electrical
a. Unless specified, our tender does not include for any
plumbing or electrical works, however it is sometimes
necessary with our works to undertake such tasks to enable
repairs to be completed. Should this occur, we will endeavour
to secure a repair by a qualified plumbing or electrical
contractor but this cost will be recoverable from you
at cost +30% and by agreeing to our tender, you are agreeing
to us being able to recover these costs from you. As we
have no knowledge, of the heating, plumbing or electrical
systems within the property, we are unable to accept any
responsibility for the condition or operation of these
systems before or after the repairs have been completed.
Should the existing systems prove not to meet current
requirements any costs involved in compliance will be
borne by the client as a variation to the contract.
Scaffolding
a. Where the estimate includes for the provision of scaffolding
by the Employer, the Company shall be consulted regarding
the nature of such scaffolding before it is erected. Generally,
working lifts are to be set 1 metre below the line of
the Helibeam installation, with the inner line of standards
set a minimum of two boards (preferably three boards)
width away from the wall.
Damp Resistance
a. Movement or fracturing can break previously adequate
damp resistance or damp proofing. In addition, removing
partial floor areas can result in loss of integrity of
damp proof membranes. This is especially so where structures
are below ground level (e.g. basements) or retain soil.
The Company cannot guarantee that walls or floors will
remain damp proof on the completion of the underpinning.
The Employer is advised to obtain the advice of a damp
proof specialist.
Trees
a. Where there is vegetation on clay soils, roots will
extract moisture causing the ground to shrink. Conversely,
if vegetation is removed, moisture may in time return
to the soil, causing it to swell. The Employer is advised
to obtain advice from a qualified Arboriculturalist of
the possible consequences of permitting to remain or removing
trees or large shrubs in the vicinity of foundations supported
on clay soils.
Safety
a. The Company undertakes to carry out the works as safely
as is practicable. The nature of the works is such that
the Employer must be aware of the inherent dangers on
the site, especially when continuing to live in the property
during the works. The Employer shall exercise due care,
and shall ensure that all those entering the site (except
the Company’s employees) are aware of the possible
dangers.
Guarantee
a. Any certificate of guarantee or liability attached
to the Company will relate only to lengths of wall to
which deep underpinning has been carried out, and not
‘phase-out’ bases or beams. By underpinning
a wall, the risk of continued or potential movement is
significantly reduced. There can be no guarantee that
movement will not occur in parts of the structure not
underpinned, or at the junction of underpinned and non-underpinned
sections of wall. Where design is the responsibility of
others, the Company’s guarantee shall not cover
that element of the works.
Site Investigations
a. Unless provided by the Employer or his/her representative,
no site investigation information is available prior to
the design of the underpinning. We strongly recommend
that trial pits. Boreholes and soil tests are carried
out to confirm the site conditions, and the design, prior
to the works being carried out. Failure to do so may result
in abortive works and/or delays, the cost of which shall
be borne by the Employer.
Matching Finishes
a. The Company will make every effort to ensure that,
where making good is carried out, this is executed to
ensure as close a match with the original as is practicable.
However, it is not always possible to achieve an exact
match of colour or texture, and no guarantee is given
in this respect.
Sub-soils
a. Sub-soils are by their location hidden from view and
no soils investigation can be exhaustive to the extent
that all conditions are known. Our recommendations are
therefore based on the information observed and collected.
Conditions may be present which were not evident in boreholes
or trial holes. Any unexpected material or ground water
found during the execution of construction works will
require a design review. Where fill material is encountered
this does not constitute evidence of contamination. With
any site, whether a fill material is encountered or not,
there is a risk of contamination and although that risk
may be small it can only be reduced further by carrying
out a desk top survey and contamination analysis. The
absence of contaminants from test results does not guarantee
a clean site. There may be pockets of contaminants not
found and there may be contaminants not detected by the
test program.
Provisional Sums
a. Where a provisional sum is shown in the Estimate the
final cost of the work to which it relates shall be calculated
at the Company’s usual rates and substituted in
the final account in place of the provisional sum.
Warranty
a. Where a guarantee is offered, issue may be refused
when the Employer fails to pay sums properly due under
the contract.
Variations
a. Any variations and additional works not priced and
agreed in writing before the commencement of the works.
Additional works
a. Shall be measured and charged (or credited
if applicable) at the rates used in preparing the Estimate
or comparable rates.
Paths
a. Employers are asked to note that the
Company does not guarantee the stability of replacement
footpaths or steps, since they are founded at ground level.
The Normal reinstatement specification comprises a minimum
75mm thick, plain concrete. This specification may be
increased, at additional cost, if required.
Schedule
of Assumptions:
Design Depth
a. The ground at and below the design depth is suitable
for the founding of the proposed scheme and that the ground
above consists of self-supporting material for hand excavation.
Footing Construction
a. The existing foundations are sound and have been constructed
in accordance with normal corbelled brickwork, strip or
trench fill construction methods which can be incorporated
into the proposed scheme and that there are no previous
attempts at underpinning, massive concrete paths, walls,
or other obstructions which may affect the progress of
the works or require removal in order to install the works.
b. It is assumed in pricing (unless trial
hole information is available at the time of tendering)
that the existing foundation comprises normal construction,
founded in accordance with the details shown on the drawing
or specification provided.
c. Where works are to be carried out below ground level
it is assumed that the details of the existing foundations
as supplied are typical and that there are no obstructions
which may affect the normal progress of the works or require
removal in order to install the works
Services
a. The Employer will advise our operatives at commencement,
of any special precautions that need to be taken during
the course of the works, and will advise the location
of electricity, water, gas or any other services passing
through the sites.
b. The position and condition of services is such that
they can be located and worked around without requiring
diversion, repair, or replacement, or the need for special
precautions or additional excavation or other works
Hours
a. The works may proceed without hindrance during the
Company’s normal working hours (Monday to Friday,
0800 hrs to 1630 hrs). By agreement, works may be carried
out outside these times, at additional cost to the contract.
Skips
a. The Highways authority will permit two skips to be
placed on the road immediately outside the property for
the disposal of spoil. In the event of this not being
possible, the Employer will allow the skips to be placed
within the boundaries of the property, and meet the additional
costs of any additional access or reinstatement requirements.
Ground water
a. Only surface water will require removal. The cost of
removing standing, running or spring water, or water from
any other source or any other work associated with, or
resulting from, the ingress of water has not been included.
Facilities
a. All electricity, water, toilet and telephone facilities
required by the operatives to effect the works expeditiously
will be supplied free of charge.
b. Suitable and safe access is to be provided by the Employer
as and when required for the purpose of the works, including
the storage of plant and materials.
Structural conditions
a. The structural condition of the property and the disposition
of loads will not have altered between the date of the
inspection and the time the works are carried out.
b.
The forces acting within the existing structure and/or
the Company’s work are those used when preparing
the design.
Making good
a. This Company is not required to carry out any works
to drains, plasterwork, rendering, decorations, plinths,
pavings, steps, floors, paths, drives, roadways, gardens,
lawns or replace plants and shrubs or turf whether disturbed
or damaged as a result of carrying out the works or access
to the works or otherwise unless specifically included
within the Estimate and accepted by the Employer as part
of the contract, or subsequently agreed as a variation.
Hindrance
a. The works can be carried out without hindrance from
third parties.
Notices
a. Before works are commenced all notices or negotiations
with adjoining owners, Statutory Authorities or other
third parties will have been served by others and completed,
and all fees, costs and disbursements, will have been
paid by others, unless specifically requested and included
within our estimate.
Reconstruction
a. Unless specifically stated in the Estimate, costs in
relation to demolition and reconstruction allow for the
re-use of existing components. No costs are included for
bringing construction up to current standards, or for
the replacement of inadequate or substandard components.
Insurance
a. The property and its contents are fully insured by
the Employer for the duration of the works for all risks
other than negligence by the Company and the relevant
Insurance Company/ies have been informed of the works.
The following will be construed
as a Variation, and valued accordingly;
a. Any additional work that is required as a result of
any difference between the above assumptions and the site
conditions or requirements of the Employer.
b. Any alterations to the proposed works and/or the Company’s
normal construction methods required by any competent
authority.
Efficacy
a. The remedial measures proposed rely upon the proviso
that the foundations of the structure are capable of adequately
transferring the applied loads to the supporting stratum.
The suggested remedial repairs are based on the assumption
that the existing foundations are not moving. There us
some resilience to small cyclic movement and it is likely
that the design will restrain the structure for some time.
If large-scale slippage/differential movement occurs in
the future it is likely that major remedial work to the
foundations will be required.
Conditions of Contract:
Definitions
‘Employer’ shall mean the Insured,
or the person/s responsible for payment under the terms
of the Contract, and who shall be signatories to the Contract.
The ‘Company’ shall mean
Documents
a. The contract documents which shall form the basis of
the Contract between the Employer and the Company shall
compromise the Estimate and/or Schedule of Works, Schedule
of Assumptions, Conditions of Contract, General Notes,
any drawings and the letter accompanying the Estimate.
Determination
This contract may be determined by the Company if;
a. The Employer fails to pay a properly issued Application
for Payment, or Invoice within the payment terms herein.
If payment is not made within these terms the Company
reserves the right to make safe and cease all work and
clear away all plant and materials. All costs arising
from such action will be added to the Contract.
b. The Employer commits any act of bankruptcy, or, being
a Company, enters into liquidation. All costs incurred
by the Company at the time of determination shall become
payable by the Employer.
Liability to pay
a. Notwithstanding any separate agreements the Employer
may have with his/her Insurance company or any other third
party, the Employer main personally liable for all payments
properly due under this Contract.
Insurance
a. Employers and Public Liability Insurance, is held by
the Company. Copies of the policy are available for inspection
upon request. Additional insurances may be arranged at
the Employer’s expense, following receipt of written
instructions. The Company will not accept liability for
claims not covered by the policies or in excess of the
stated liabilities.
Disputes
a. Any dispute or difference arising between the parties
under this Contract or any Guarantee whether qualified
or not, issued by the Company under this contract, shall
be referred to a single arbitrator to be agreed by the
parties to the Contract or their successors in title,
or in default of agreement, to be nominated by the President
for the time being of the Institution of Civil Engineers
in accordance with and subject to the provisions of the
Arbitration Act 1950 or any statutory modification or
re-enactment for the time being in force.
Acceptance period
a. Unless otherwise stated, the Estimate shall remain
open for acceptance for a period of two calendar months
from the date of preparation. Estimates not accepted during
this period shall be withdrawn without notice.
Acceptance
a. Admission of the Company’s employees onto the
site shall constitute unconditional acceptance of the
Company’s offer.
Fluctuations
a. Up to the date of expiry of the Estimate, the Company
will hold its prices and rates fixed in respect of labour,
plant, material or transport costs, but not in respect
of any increases in contribution levies or taxes payable
by the Company. After the date of expiry the Company reserves
the right to apply any increases, which may apply.
Start/Finish Dates
a. The starting date shall be agreed between the Employer
and the Company. Every effort will be made to commence
in accordance with the wishes of the Employer but the
Company will not be responsible for additional costs incurred
by the Employer if delays occur as a result of late commencement
due to non-availability of resources, weather conditions,
additional works or other such factors which are outside
the control of the Company.
Value added tax
a. All prices in the Estimate are exclusive of V.A.T.
which, will be charged in addition at the rate ruling
at the time the works are carried out.
Provisional Sums
a. Where a provisional sum is shown in the Estimate, the
final cost of the work to which it relates shall be calculated
at the Company’s usual rate and substituted in the
final account in place of the provisional sum.
Variations Additional Works
a. Any variations and additional works not priced and
agreed in writing before the commencement of the works
shall be measured and charged (or credited if applicable)
at the rates used in preparing the Estimate.
Payment
a. The Company reserves the right to issue upon commencement
of the works an Application for Payment for 25% of the
contract sum to be paid within 14 days. During the works,
but at intervals of not less than 14 days, the Company
will issue an Application for Payment or Invoices to the
value of works completed, plus materials on site, to be
paid within 14 days. The Employer shall not withhold sums
of money vexatiously or not commensurate with the value
of incomplete works or items in dispute.
Interest
a. If the Employer has not paid in full any Application
for Payment or Invoice in accordance with the Company’s
terms of payment, the Employer shall pay the Company interest
on any balance outstanding at the rate of 8% above the
base rate of the Company’s bankers (subject to a
minimum of 10%) calculated on a daily basis and calculated
on a daily basis and calculated from the date due for
payment to the actual date of payment in addition to late
payment compensation payable on each late paid invoice
as per published late payment guidelines. The date of
payment shall be taken as the date on which the payment
is credited to the Company’s account.
Safety
a. The Employer should note that the works involve deep
excavations and he/she shall exercise due care and attention
when entering the site and shall advise those who legitimately
have access to the site (except the Company’s employees)
of the inherent dangers and difficulties of access.
Limit of Liability
a. Whether or not a Guarantee is issued, the Company’s
liability for any loss or damage of whatever nature (excepting
personal injury or death) and however arising shall be
limited to the contract price as adjusted by the Retail
Price Index or any statutory replacement.
Liability for advice
a. Subject to the Unfair Contract Terms Act 1977 the Company
shall not be liable for any loss or damage whatsoever
arising from:
i) Reliance on any advice or recommendation by the Company
whether oral or in writing unless the Company itself has
performed the works to which the advice or recommendation
relates.
ii) Any work whatsoever unless carried out by the Company
whether or not the work was carried out or purported to
have been carried out in accordance with the advice or
recommendation of the Company whether orally or in writing.
Reserved right
a. The Company without notice or reaching agreement with
the Employer reserves the right to change the works specified
and estimated providing that such alteration shall substantially
achieve the same object as the original works and that
any such change shall not involve the Employer in additional
cost to the Company.
Notices and Fees
a. The Estimate and offer to carry out the works assumes
that all Statutory Notices and consents have been applied
for and received by the Employer before commencement of
the works by the submission of a Building Notice. If the
Employer wishes to pursue a ‘Full Plans’ approval,
he/she should discuss the matter with his/her professional
adviser or the Company. Any fees or costs in connection
with notices or submissions to any authority, and incurred
by the Company in pursuance of the works, will be charged
to the Employer at cost plus 15%. Additional works required
above those included in the Estimate, where necessary
in order to comply with the requirements of Building Control
or other party, will be charged in additional to the Contract
price.
Completion
a. The Company shall endeavour to complete the works in
accordance with the stated period and/or in accordance
with the Employer’s instructions provided that the
Company shall not be liable for and delay due to any cause
beyond its control.
Overtime
a. The Estimate is based upon the Company’s normal
working hours. The Company shall be entitled to increase
the contract sum and the rates if overtime working is
required. The Company’s normal working hours are
Monday to Friday, 0800 hrs to 1630 hrs.
Lien
a. All goods supplied by the Company remain the property
of the Company until paid for in full. Where payment in
full is not received, the Company shall have the right
without fear of trespass to enter the premises to recover
such goods as necessary to recover the debt.
Validity
a. It is hereby agreed and declared that each clause of
this Agreement shall be read and construed independently
of the others so that if any one or more of such clauses
shall be judged to be void or unreasonable but be valid
if part of the working thereof were deleted, the said
clauses shall be deemed to apply with such modifications
as may be necessary to make them valid and effective and
any such modification shall not thereby affect the validity
or any other restriction contained therein.
|